1. Project Overview
Project Name: Deployment of a 100 kWh BESS System at an Electric Vehicle Charging Station
Location: Phu Tho, Vietnam
Implementation Period: February 2026

2. Project Objectives
-
Optimize energy utilization from the rooftop solar power system.
-
Help reduce load on the power grid during peak hours.
-
Increase revenue and profitability for the charging station.
-
Provide a green, clean, and sustainable energy solution.
3. Key Technical Specifications
| Item | Details |
|---|---|
| System Capacity | 100 kWh |
| Battery Type | Li-ion (LFP) |
| PCS | 50 kW |
| Features | Bidirectional charging/discharging, intelligent management via EMS |
| Monitoring System | Remote monitoring via IoT platform |
| Safety Protection | Integrated BMS, fire and explosion prevention, circuit isolation, overvoltage protection |
4. Challenges & Solutions
-
Challenges:
-
Significant fluctuations in electric vehicle charging loads, placing pressure on the urban power grid.
-
Complexity in achieving seamless integration between the Solar PV system and the BESS.
-
Limitations in the capacity of the local medium-voltage distribution lines.
Solutions:
-
Deliver an end-to-end solution from Solar PV to BESS, ensuring full system integration and synchronization.
-
Integrate an Energy Management System (EMS) for intelligent power dispatch and optimization.
-
Install remote monitoring equipment with early warning features for battery and system status.
5. Expected Outcomes
-
-
Reduce operating costs of the charging station by utilizing off-peak electricity.
-
Ensure stable delivery of 100% charging capacity during peak hours without interruptions.
-
Alleviate pressure on the local power grid during peak demand periods.
-
Contribute to enhancing the image of a green electric vehicle charging station in Phu Tho.